Construction of Stemac plant in Itumbiara
Customer: Stemac S/A Grupos Geradores
Location: Itumbiara/GO
Project Challenge: Construction of the plant and accesses in short term
Artec Approach: Among the technologies adopted, the company executed the concrete floor reinforced with high-strength steel fibers and polyester, with 8,000 kg/m² load capacity, using for application one imported, laser screed-type paver that enabled a daily release of 350m³ of concrete and finishing more than 2,000m² per day. The solution resulted in the advance of the schedule in the order of 15% of the final delivery term of the work.
- Project Progress
-
Concluded100%
- Last update in 25/01/2021 at 11:35